Electricity arrangements are nearing completion, streetlight poles have been installed, and the CDA Chairman has directed officials to hand over plots to allottees without delay.

RESPONSIVE LEADERBOARD AD AREA

Picture of By Waqas Malik

By Waqas Malik

Posted on: November 11, 2026

Electricity arrangements are nearing completion, streetlight poles have been installed, and the CDA Chairman has directed officials to hand over plots to allottees without delay.

ISLAMABAD: The Capital Development Authority (CDA) has reported that approximately 92% of the basic infrastructure work in Sector C-14 has been completed.

Chairman CDA and Chief Commissioner Islamabad Sohail Ashraf visited the sector on November 10 to review the progress of ongoing development activities.

During the briefing, officials informed him that development work was continuing at a fast pace. They also shared updates on electricity arrangements, streetlights, road signboards and landscaping.

Electricity arrangements nearing completion

According to the CDA, arrangements for electricity supply in Sector C-14 have entered their final stages.

The installation of light poles along the main roads has been completed, while signboards are being installed on the sector’s main roads and streets. Landscaping and horticulture work is also underway.

CDA Chairman directs early handover of plots

During the visit, Sohail Ashraf directed the relevant officers to provide possession of plots to allottees without delay.

He also instructed officials to complete the remaining development work on a priority basis and ensure regular monitoring of development projects in new sectors.

The CDA Chairman said that the development of new sectors was among the administration’s top priorities. He added that completing these projects would improve Islamabad’s infrastructure and provide better residential facilities.

Remaining work still needs to be completed

With around 92% of basic infrastructure work reported as complete, Sector C-14 is moving closer to the next stage of development.

However, electricity arrangements, signboard installation, landscaping and other remaining works still need to be completed. The timely handover of plots will also be important for allottees waiting to take possession.

RESPONSIVE LEADERBOARD AD AREA

Recommended for you

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

CDA Reports 92% Infrastructure Work Completed in Islamabad’s Sector C-14
IESCO Announces Power Shutdown Schedule for November 11 Across Six Circles
954 Acres of Pakistan Railways Land Encroached in Karachi Division
Margalla Avenue Extension and Sangjani Interchange Reach 35% Completion
IESCO Announces Power Shutdown Schedule for November 10 Across Six Circles
Government Debate Grows Over Proposal to Create 12 Provinces in Pakistan