A dispute over land auctioned for warehouses has led to sealed construction sites, legal proceedings and a fresh review by the CDA board.
ISLAMABAD: The Capital Development Authority (CDA) and Pakistan Railways are involved in a dispute over the ownership and use of a plot of land in Sector I-9, where construction of godowns and warehouses has been stopped.
According to a report published by Dawn on November 13, the CDA board heard Pakistan Railways officials and lawyers representing the leaseholders on Thursday to review the matter.
Pakistan Railways auctioned plots along Dry Port Road near Margalla Railway Station in I-9 last year for the construction of godowns and warehouses. The railway authorities subsequently approved the building plans.
However, the CDA later sealed the under-construction buildings, describing the work as unauthorised and an encroachment on its right of way along Service Road North.
Dispute Over Land Ownership
Pakistan Railways maintains that the disputed land belongs to the department and remains under its administrative control. The leaseholders have also argued that the land was acquired from the CDA after payment and that Pakistan Railways had the authority to approve their building plans.
The CDA, on the other hand, says the land forms part of its right of way and that construction cannot be carried out there under its regulations.
Islamabad High Court’s Observations
The matter was also taken to the Islamabad High Court after the leaseholder challenged the sealing of the construction sites.
The court observed that ownership or administrative control by Pakistan Railways, lease agreements and building-plan approvals issued by its officials do not automatically exempt the land from planning and building-control laws applicable in Islamabad.
The court also noted that the legality of the construction depends on factors including land ownership, permitted land use, building regulations and whether the structures affect a public right of way.
Last month, the court directed the CDA to examine the leaseholders’ representations, the relevant Pakistan Railways letter dated July 9, 2026, and supporting documents. It ordered the authority to issue a reasoned decision within 30 days after receiving the certified copy of the judgment.
CDA Board Reviews the Case
Following the court’s directions, the CDA board heard the railway officials and the leaseholders’ lawyers. The CDA’s legal representative also presented the authority’s position.
CDA sources told Dawn that the authority would review the available records before issuing its decision.
The dispute highlights the importance of clear land ownership records, building approvals and planning regulations for commercial construction projects in Islamabad. The final decision is expected to clarify the position of the disputed land and the future of the warehouse construction.