Authority raises concerns over development without an approved NOC and alleged encroachment on the Soan River
ISLAMABAD: The Capital Development Authority (CDA) has issued a show-cause notice to the Federal Employees Cooperative Housing Society over the development of Jinnah Garden Phase-II on Kahuta Road without an approved No-Objection Certificate (NOC) and alleged encroachment on the Soan River.
The notice, dated November 17, follows a site inspection conducted on November 9 by CDA officials along with a representative of the housing society. The authority has directed the society’s secretary to submit a written explanation within 10 days and clarify why legal action should not be taken over the reported violations.
CDA Reports Construction Along Soan River
According to the notice, the inspection team found a steel deck structure built along the existing rock formation within the designated right of way of the Soan River.
The authority stated that around 1,200 feet of a wall had been constructed along the river. Of this length, approximately 600 feet was within the approved boundary of the housing scheme, while the remaining 600 feet was outside the approved scheme area.
CDA also reported that a site office had been constructed near a park and sitting area after a portion of the existing rock was excavated.
Sewage Treatment Plant Land Also Flagged
The notice further stated that land reserved for a sewage treatment plant (STP) in the approved layout plan had been developed as a park and sitting area, with part of it falling within the river’s right of way.
The authority also noted that around 400 kanals had been developed with paved roads, while land clearing and efforts to secure possession were still underway in the housing scheme.
CDA Warns of Possible Legal Action
CDA has asked the society to explain the reported violations within 10 days. The notice warns that if the society fails to comply, the authority may remove or demolish illegal structures and stop the unauthorised use of land with police assistance.
The society’s secretary has also been offered an opportunity to appear for a personal hearing within the same 10-day period and present an explanation.
The notice is a show-cause action and does not itself establish a final decision on the allegations. The society’s response and any further action by CDA remain awaited.