After remaining pending for nearly four decades, development work in Islamabad’s Sector E-12 is moving forward, with more than 68 percent of the work now completed, according to the Capital Development Authority (CDA).
The authority says the process of handing over plot possession to allottees is also continuing. Several allottees have submitted applications to take possession of their plots and begin construction of their homes.
According to the development update, road work has been completed in several streets across different parts of the sector. TST work has been completed in 25 streets of E-12/1, 31 streets of E-12/2 and 15 streets of E-12/3. Earthwork has also been completed in the remaining streets of E-12/1, while base and earthwork are progressing in other areas.
In E-12/4, earthwork has been completed, while base, sub-base, drainage and sewerage work is ongoing.
Work is also progressing on nearby roads. Asphalt work is underway on Service Road Khayaban-e-Iqbal and Margalla Road, while earthwork, base, sub-base and drainage work on Service Road East has been completed. Underground work to provide electricity to the sector is also continuing.
The CDA further stated that around 1,135 kanals of land had been recovered from illegal occupation to remove obstacles to development. Landscaping and plantation work in green belts is also underway.
CDA Chairman Sohail Ashraf has directed officials to remove remaining obstacles and complete the pending development work on a priority basis.
The authority says development of new sectors and improved residential facilities are among its priorities as Islamabad’s population continues to grow.